Problem:
Compute the PI statistic for Project Z and advise the firm whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Explain in detail and show all work.
Time: 0 1 2 3 4 5
Cash flow -$1,000 $350 $480 $650 $300 $100