Problem:
1. Hastings Hardwood Floors installs oak and other hardwood floors in homes and businesses. The company uses an activity-based costing system for its overhead costs. The company has provided the following data concerning its annual overhead costs and its activity based costing system:
Overhead costs:
|
|
Production overhead
|
$110,000
|
Office expense
|
130,000
|
Total
|
$240,000
|
Distribution of resource consumption:
Activity Cost Pools
|
Installing Floor
|
Job Supports
|
Other
|
Total
|
Production overhead
|
50%
|
30%
|
20%
|
100%
|
Office expense
|
5%
|
65%
|
30%
|
100%
|
The "Other" activity cost pool consists of the costs of idle capacity and organization sustaining costs.
The amount of activity for the year is as follows:
Activity Cost Pool
|
Annual Activity
|
Installing floors
|
400 squares
|
Job support
|
100 jobs
|
Other
|
Not applicable
|
A ""square"" is a measure of area that is roughly equivalent to1,000 square feet.
Required:
a. Prepare the first-stage allocation of overhead costs to the activity cost pools by filling in the table below:
|
Installing
|
Job
|
|
|
|
Floors
|
Support
|
Other
|
Total
|
Production overhead
|
|
|
|
|
Office expense
|
|
|
|
|
Total
|
|
|
|
|
b. Compute the activity rates (i.e., cost per unit of activity)for the Installing Floors and Job Support activity cost pools by filling in the table below:
|
Installing
|
Job
|
|
Floors
|
Support
|
Production overhead
|
|
|
Office expense
|
|
|
Total
|
|
|
c. Compute the overhead cost, according to the activity-based costing system, of a job that involves installing 1.8 squares.