Compute the npv for project x with the cash flows shown


Compute the NPV for Project X with the cash flows shown below if the appropriate cost of capital is 10 percent.

Time:     0              1              2              3              4              5

Cash flow:           -150       -150       0              250         225         200

$465.69

$179.33

$211.98

$163.02