An overhaul of a firm's outdated production facilities is expected to cost £100,000. The improvement to the firm's net cash flow over the next five years is expected to be as follows:
Year 1
|
£40,000
|
Year 2
|
£35,000
|
Year 3
|
£30,000
|
Year 4
|
£20,000
|
Year 5
|
£1 0,000.
|
Calculate the net present value using the discount rates of 10, 12 and 14 per cent.