Problem 1:-
|
Standard Quantity or Hours
|
Standard Price or Rate
|
|
Direct materials
|
6.8 pounds
|
$ 2.90 per pound
|
|
Direct labor
|
0.2 hours
|
$ 9 per hour
|
|
During the most recent month, the following activity was recorded:
|
a.
|
15,100 pounds of material were purchased at a cost of $2.60 per pound.
|
b.
|
All of the material purchased was used to produce 2,000 units of Zoom.
|
c.
|
300 hours of direct labor time were recorded at a total labor cost of $3,300.
|
Required:
1. Compute the materials price and quantity variances for the month.
2. Compute the labor rate and efficiency variances for the month.