Discuss the below:
Q: The manager of a crew that installs carpeting has tracked the crew’s output over the past several weeks, obtaining these figures:
Week
|
Crew Size
|
Yards Installed
|
1
|
4
|
96
|
2
|
3
|
67
|
3
|
4
|
98
|
4
|
2
|
50
|
5
|
3
|
66
|
6
|
2
|
52
|
Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.)
Week
|
Crew size
|
Labour productivity
(Yards/Person)
|
|
1
|
4
|
|
|
2
|
3
|
|
|
3
|
4
|
|
|
4
|
2
|
|
|
5
|
3
|
|
|
6
|
2
|
|