The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures:
Week
|
Crew Size
|
Yards Installed
|
1
|
4
|
96
|
2
|
3
|
72
|
3
|
4
|
92
|
4
|
2
|
50
|
5
|
3
|
69
|
6
|
2
|
52
|
Compute the labor productivity for each of the weeks. On the basis of your calculations, what can you conclude about crew size and productivity?