Compute the labor productivity


The manager of a new crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures:

Week Crew Size Yards Installed

1 4 96

2 3 72

3 4 92

4 2 50

5 3 69

6 2 52

Compute the labor productivity for each of the weeks. On the basis of your calculations, what can you conclude about crew size and productivity?