Compute the eoq for the overall cycle


Problem: In European Metals, we examined a "cyclic schedule," in which we produce each item in turn, until all items have been produced; then we start over at the beginning. Refer to the EuroMet spreadsheet.

Q1. If you increase the slack required from 0.05 to 0.075 (EuroMet cell E31), the costs (see Cost Comparison worksheet) go down. This is surprising since inventory cost increases. The reason for the reduction is that the setup cost and other costs would imply an EOQ value of around 2361, greater than the current value of 1918 (cycle time in hours, 92.76, times demand per hour, 20.68).

Use the total setup cost of 24 items times 0.5 hour per setup times $160 per hour of setup; also use the total demand rate per hour for all items of 20.68, and the inventory cost per hour per unit of $480*0.26/(365*24).

Compute the EOQ for the overall cycle; i.e., act as if the demand was for one aggregate item. Verify the 2361 value. Then, how many days of supply is that; that is, what cycle time is implied?


Attachment:- EuroMet.rar

Solution Preview :

Prepared by a verified Expert
Other Management: Compute the eoq for the overall cycle
Reference No:- TGS02003056

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)