Assignment:
Intro- Supply Chain Management
Problem: Line Balancing
Your product has the following tasks and predecessors.
Task Predecessor Average Time (sec)
A none 40
B none 60
C B 30
D C 30
E A, D 30
F E 30
1- Use a takt time of 120 seconds and follow the "most following tasks" heuristic rule to assign these tasks to the work stations. Show which tasks are assigned to each workstation.
2- Compute the efficiency and percent idle time for the system.