Compute the discounted payback statistic for Project C if the appropriate cost of capital is 9 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project C
Time: 0 1 2 3 4 5
Cash flow –$1,800 $800 $720 $760 $460 $260
Discounted payback period years