Compute the discounted payback period for a project with the following cash flows, if the company's discount rate is 12%.
Initial outlay = $450
Cash flows: Year 1 = $325
Year 2 = $65
Year 3 = $100
A) 3.43 years
B) 3.17 years
C) 2.88 years
D) 2.6 years