Cabot Company collected the following data regarding production of one of its products. Compute the direct materials price variance. Direct Materials Standard $12 finished unit; Actual direct materials used 243,00lbs; Actual finished units produced 40,000 units; Actual cost of direct materials used $483,570. The answers I have are: a. $2,430 unfavorable. b. $3,570 unfavorable. c. $2,430 favorable. d. $6,000 unfavorable. e. $3,570 favorable.