Becker company applies overhead at a rate of $26 per direct labor hour. Budgeted labor hours were 25,0000; actual labor hours exceeded the budget by 1,600 hours. Overhead was overspilled by $3,758.
(a) Compute the budgeted overhead for the year
(b) Compute actual overhead for the year