An insurance claims work area has five claims waiting for processing as follows:
Job A: process time: 15 Due date: 26
Job B: process time: 21 Due date: 32
Job C: process time: 20 Due date: 35
Job D: process time: 10 Due date: 30
Job E: process time: 12 Due date: 23
Compute the average flow time, tardiness, and lateness for the following sequences: SPT sequence, EDD sequence, and sequence B-A-E-C-D
What sequencing rule do you recommend and why?