Compute the abc indirect manufacturing cost per unit


Question:

Computing indirect manufacturing costs per unit

Day, Corp., is considering the use of activity-based costing. The following information is provided for the production of two product lines:

Activity

Cost

Cost Driver

Setup

$ 106,000

Number of setups

Machine maintenance

55,000

Machine hours

Total indirect manufacturing costs

$ 161,000



Product A

Product B

Total

Direct labor hours

6,500

5,500

12,000

Number of setups

20

180

200

Number of machine hours

1,600

2,400

4,000

Day plans to produce 400 units of Product A and 375 units of Product B.

Requirement

1. Compute the ABC indirect manufacturing cost per unit for each product.