Oriole Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $1,860,000 on March 1, $1,260,000 on June 1, and $3,080,650 on December 31. Compute Oriole's weighted-average accumulated expenditures for interest capitalization purposes.