Question: If I was considering the following projects which project should be accepted if the required rate of return for the projects is 10 percent? Compute NPVs and IRRs for both projects.
Year Project A Project B
0 (25000) (25000)
1 10000 0
2 9000 0
3 7000 0
4 6000 36000