The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival.
| ob | 
Processing  Time (Days) | 
Due Date  (Days) | 
Remaining Number  of Operations | 
| A | 
8         | 
20 | 
2 | 
| B | 
10         | 
18 | 
4 | 
| C | 
5         | 
25 | 
5 | 
| D | 
11         | 
17 | 
3 | 
| E | 
9         | 
35 | 
4 | 
Required:
Question 1) Determine the processing sequence at the first work center using each of these rules: (1) First come, first served, (2) Slack per operation.
Question 2) Compute the effectiveness of each rule using each of these measures: (1) average completion time, (2) average number of jobs at the work center. Solve the given numerical problem and illustrate step by step calculation.