Assignment Task:
Opaskwayak Inc. bottles pure spring water from lakes in northern Manitoba. The lakes are on First Nations property, and the band is the majority shareholder in the company. The only cost for the water is the cost of transportation and purification. The company is very careful not to overtax the water systems when it takes water. It also ensures sustainability for the land.
Opaskwayak currently produces three different products from the spring water: still water, carbonated water, and a cranberry-flavored carbonated version. The process for creating the various products is as follows: All products start with the piping of the water to the bottling plant. At the plant, the water undergoes a thorough distillation process. 1% of the volume is lost in the distillation process. For still water, the water is bottled at this point. For carbonated water, the water goes from this split-off point to the Carbonation department. After carbonation, a percentage of the product is bottled, and the remainder is moved to the Fruit department. In the Fruit department, the cranberries are sorted, juiced, and boiled into syrup. The syrup is added to the carbonated water, and the final product is bottled.
The following information was reported for the most recent period:
Department
|
Transportation
|
Purification
|
Carbonation
|
Fruit
|
Bottling
|
Direct materials
|
-
|
-
|
$1,029,500
|
$320,760
|
$130,680
|
Direct labour
|
$87,500
|
$75,750
|
$145,000
|
$180,000
|
$218,400
|
Planned manufacturing
|
|
|
|
|
|
|
|
|
|
|
|
overhead
|
$1,657,250
|
$560,000
|
$675,850
|
$356,000
|
$6,800,000
|
Actual manufacturing overhead
|
|
|
|
|
|
|
|
|
|
|
$1,754,235
|
$485,000
|
$669,880
|
$376,128
|
$6,875,000
|
Planned machine hours
|
26,200
|
8,800
|
20,000
|
20,000
|
2,496
|
Actual machine hours
|
26,208
|
8,850
|
19,500
|
20,100
|
2,496
|
Planned direct labour hours
|
|
|
|
|
|
|
|
|
|
|
5,250
|
5,050
|
10,000
|
12,000
|
10,000
|
Actual direct labour hours
|
|
|
|
|
|
|
|
|
|
|
5,650
|
5,000
|
10,050
|
11,990
|
12,000
|
Volume in litres
|
120,000,000
|
118,800,000
|
41,580,000
|
5,940,000
|
118,800,000
|
In the current period the following production occurred:
- 60% of the purified volume was bottled as still water.
- 35% of the purified volume was bottled as carbonated water, and the remainder was bottled as cranberry-flavored carbonated water.
A direct labour hour is the cost driver in the Transportation and Purification departments. All other departments are driven by machine hours.
In the Fruit department, the accountant has analyzed the activities and has arrived at the following:
Activity
|
Cost
|
Driver
|
Volume
|
Cost per unit
|
Washing
|
$24,175
|
Kg of fruit
|
3,000,000
|
$0.01
|
Sorting
|
115,000
|
Kg of fruit
|
3,000,000
|
0.0383
|
Juicing
|
116,150
|
Kg of fruit
|
2,950,000
|
0.0394
|
Boiling
|
100,675
|
Litres of juice
|
5,900,000
|
0.0171
|
For the last batch of the year, Opaskwayak processed 1,000,000 pre-purification litres with the following direct labour hours and machine hours:
Department
|
Direct labour hours
|
Machine hours
|
Transportation
|
50
|
221
|
Purification
|
28
|
75
|
Carbonation
|
95
|
192
|
Fruit
|
100
|
167
|
Bottling
|
85
|
20
|
Processing this final batch took 2,500 kilograms of cranberries, of which 2,458 kilograms remained after sorting. This produced 4,916 litres of juice. Bottling costs are allocated on the basis of volume processed. Assume that $24,520 in direct materials is added in Carbonation, $2,675 in Fruit, and $1,090 in Bottling.
Required:
Part 1: Compute each department's manufacturing overhead rate, assuming that Opaskwayak uses a normal department rate based on the planned manufacturing overhead.
Part 2: Calculate the total joint costs for the last batch of the year using the manufacturing overhead rates calculated in part (a).
Part 3: Calculate the cost of bottling and carbonating the water and adding the fruit syrup for the last batch of the year based on the manufacturing overhead rates calculated in part (a).
Part 4: Determine how much of each product was produced in the final batch based on the current production breakdown.
Part 5: Using the net realizable value method and the planned amounts, as well as the amounts calculated in parts (c) and (d), allocate the joint costs of Transportation and Purification to the final batch produced.
Part 6: Using the joint cost calculated in question 2e; calculate the cost of the final batch of cranberry-flavored carbonated water using activity-based costing for the costs in the Fruit department.
The professionals of Manufacturing Overhead Rate Assignment Help service are always there to assist you in all your academic needs.
Tags: Manufacturing Overhead Rate Assignment Help, Manufacturing Overhead Rate Homework Help, Manufacturing Overhead Rate Coursework, Manufacturing Overhead Rate Solved Assignments, Manufacturing Overhead Rates Assignment Help, Manufacturing Overhead Rates Homework Help