Production order quantity problem has annual demand = 3000, daily demand rate = 10, and daily production rate = 50. Production order quantity for problem is about 612 units. Annual setup costs for this problem are roughly:
Holding cost info is not given with this question, it asks to solve question without it.
a) $4.90
b) $50
c) $300
d) $490
e) $980