Compute a linear trend line for freight car loadings


Task:

Please help to build a spreadsheet to figure out the following:

Freight car loadings over an 18-week period at a busy port are:

Week Number
1      220
2      245
3      293
4      275
5      332
6      310
7      350
8      360
9      427
10    380
11    432
12    450
13    477
14    475
15    538
16    510
17    532
18    541

a) Compute a linear trend line for freight car loadings:

Y=___+___t.

b) Use the trend equation to predict loadings for weeks 25 and 26:

The forecasted demand for week 25 and 26 is ____ and ____ respectively.

c) The manager intends to install new equipment when the volume reaches 829 loadings per week. Assuming the current trend continues, the loading volume will reach that level in approximately what week?

It would take approximately _15_ more weeks.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Compute a linear trend line for freight car loadings
Reference No:- TGS01939310

Now Priced at $25 (50% Discount)

Recommended (98%)

Rated (4.3/5)