Using the solution from Problem 5 and given the list of crash times and costs, determine the new diagram and times.
Assume for every day you complete the project ahead schedule you recieve a $60 bonus payment.
Question 5 Solution:
Critical Path = ABDFG Total Project Time = 42
PERT Time |
11 |
8 |
6 |
8 |
10 |
4 |
11 |
|
|
Total Cost |
|
|
|
Maximum |
Activity |
Normal |
Crash |
Normal |
Crash |
Reduction |
A |
11 |
4 |
150 |
550 |
7 |
B |
8 |
3 |
300 |
450 |
5 |
C |
6 |
6 |
600 |
750 |
0 |
D |
8 |
4 |
100 |
100 |
4 |
E |
10 |
5 |
650 |
680 |
5 |
F |
4 |
1 |
750 |
945 |
3 |
G |
11 |
2 |
225 |
300 |
9 |
Total Crash Costs =
New Crashed Project Time =