Given this network plan, complete the following activities:
1. Complete the network diagram by conducting a forward and backward pass through the network.Compute the early/late start time,early/late finish time,and slack time for each activity
2. What is the project duration?
3. What is the critical path of this network?
4. Using any approach you wish (e.g., trial and error) develop a loading chart forthe projectresources: Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.
5. Using the resourceloading chart, nowcompute the early/late start time, early/late finish time, and slack time for your project. Illustrate thisnew resource constrainednetwork in a network diagram.
6. Complete the resource activity schedule.
7. For the new network, what is thenewproject duration?
8. Which activities are now critical?