Complete the MRP schedule for the product below. Product A Lot Size = 75 Safety Stock = 50 Lead Time = 1 week Allocated = 100 in hand =300 WEEKS 1 2 3 4 5 Gross requirement 500 700 400 500 Scheduled receipt 600 Available on hand 300+600-100-50=750 Net requirements Planned order receipts Planned order releases