Classroom Exercise: Small Decorating Project
Activity ID
|
Description
|
Duration (days)
|
Dependency(ies) and Type (FS, SS, SF, FF)
|
1
|
Decorate Room (Summary Task)
|
-
|
-
|
2
|
Remove furnishings
|
1
|
|
3
|
Fetch Paint
|
1
|
|
4
|
Fetch wallpaper
|
1
|
|
5
|
Strip walls
|
4
|
|
6
|
Paint ceiling and woodwork
|
2
|
|
7
|
Hang wallpaper
|
5
|
|
8
|
Replace furnishings
|
1
|
|
9
|
Tidy up, relax and brag about your DIY skills
|
1
|
|
Using the activity table above:
Complete the Dependency column of the table and include the dependencies and types of dependency for each activity
Produce a Project Schedule Network diagram for the project
Produce a critical path method diagram and identify the critical path of the project.
Determine the maximum project duration, assuming two units of resource that you may allocate however you wish
Produce a Gantt chart Key:
FS: Finish to Start: activity can only start when predecessor is finished regardless of resource availability SS: Start to Start: Activity and its predecessor may start simultaneously if resources are available
SF: Start to Finish: Activity must finish before predecessor may start
FF: Finish to Finish: Activity must finish at the same time as its predecessor