Compare the cost of the two projects shown below on the basis of their Capitalized costs. Use an interest rate of 10% per year.
Project C Project D
First Cost, $ -50,000 -250,000
Maintenance cost, $/year -10,000 -3,000
Salvage Value, $ 2,000 25,000
Life, years 4 ∞