Sandler Corporation bases its predetermined overhead rate on estimated machine hrs for the upcoming year. Data for the upcoming year appear shown below.
Estimated machine hrs 73,000
Estimated variable manufacturing overhead $3.49 per machine hour
Estimated total fixed manufacturing overhead $ 838,770
Required:
Calculate the company's predetermined overhead rate.