Company is setting up an assembly line to produce cellular


Company is setting up an assembly line to produce cellular phones. They intend to use line balancing with the longest- task- time heuristic. They know the demand part per hour is 40 phones and the productive time per hour is 54 minutes. Displayed below is the data they have collected

Task       time(in minutes)           predecessors

A                 0.40                                    none

B                    1.20                                  A

C                     0.90                                    A

D                     0.70                                    B

E                      0.60                                        B

F                        0.35                                       C

G                         1.00                                D, E

H                           0.80                               F,G

I                            0.50                                  H 

 

What is the cycle time?

What is the theoretical minimum number of work stations?

What tasks are assigned to the first work station?

How many work stations are needed for the entire line?

What is the assembly - line efficiency?