Question: Company ABC estimates its weighted average cost of capital (WACC) is 10.5%; it has the following list of capital budgeting projects (and their associated rates of return); each project's projected cost is $1 million. Which projects should it undertake?
Project |
Rate of Return |
A |
12.0% |
B |
11.5% |
C |
10.5% |
D |
10.2% |
E |
10.7% |