Christophers cranks uses a machine that can produce 100


Christopher's Cranks uses a machine that can produce 100 cranks per hour. The firm operates 12 hours per day, five days per week. Due to regularly scheduled preventive maintenance, the firm expects the machine to be running during approximately 95% of the available time. Based on experience with other products, the firm expects to achieve an efficiency level for the cranks of 85%. What is the expected weekly output of cranks for this company?

  1. A-5100 
  2. B-5700 
  3. C-4845
  4. D-969 
  5. E-6783 
  6. SHOW COMPUTATION

 

 

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Christophers cranks uses a machine that can produce 100