Chicago's Hard Rock Hotel distributes a mean of 900 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of 95 towels per day. The laundry firm that has the contract requires a 4-day lead time. the hotel expects a 99% service level to satisfy high guest expectations.
What is the re-order point?
What is the safety stock?