1. One limitation of the PERT/CPM approach to project management is that they fail to eliminate conflicts created when there are shared resources.
True
False
2. Which of the following is not one of the six key decisions in project management?
Deciding which projects to implement
Managing and controlling project resources
Selecting a project name
Selecting the project manager
Selecting the project team
3. In a project network, the critical path is the sequence of activities which has the:
most events.
shortest duration.
most activities.
least slack.
greatest variance.
4. Centralized purchasing is a strategy designed for small businesses.
True
False