Cave Creek Industrial Works has the following standards for one of its products.

Direct Material (3ft / $4)     $12.00

Direct Labor (.4hr / $12)      $ 4.80

During the most recent year, the following actual results were recorded.

Production        6,000

Units Direct Material (11,750ft / $5.20) $61,100

Direct Labor (2,900Hr / $10.20)    $29,580

1. Calculate the Materials Price Variance

2. Calculate the Materials Usage Variance

3. Calculate the Labor Rate Variance

4. Calculate the Labor Efficiency Variance