Capital budgeting-appropriate constraint


Question: Consider a capital budgeting example with 5 projects from which to select. Let x1 = 1 if project a is selected, 0 if not, for a = 1, 2, 3, 4, 5. Conditions are independent. Projects cost $100, $200, $150, $75, and $300 respectively. The budget is $450. Write the appropriate constraint for the following condition. If project 1 is chosen, project 5 must not be chosen.

Solution Preview :

Prepared by a verified Expert
Finance Basics: Capital budgeting-appropriate constraint
Reference No:- TGS01816033

Now Priced at $20 (50% Discount)