A four year financial project ha net cash flows of $20,000;$25,000; $30,000 ; $50,000 in the next four years. It will cost $75,000 to implement the project. If the required rate of return is 0.2 conduct a discounted cash flow calculation to determine the NPV. Show all steps and calculations.