Calculating the direct labor rate and time variances


Response to the following problem:

Alpine Bicycle Company manufactures mountain bikes. The following data for May of the current year are available:

Quantity of direct labor used ............... 600 hrs.

Actual rate for direct labor ........... $12.50 per hr.

Bicycles completed in May ...................... 280

Standard direct labor per bicycle .............. 2 hrs.

Standard rate for direct labor ......... $12.75 per hr.

Planned bicycles for May .......................... 310

Determine the direct labor rate and time variances.

Solution Preview :

Prepared by a verified Expert
Cost Accounting: Calculating the direct labor rate and time variances
Reference No:- TGS02074601

Now Priced at $20 (50% Discount)

Recommended (99%)