You are the project manager of the Carpet Installation Project for a new building. Your BAC is $600,000. You are now 40% complete with the project though your plan called for you to be 45% complete with the work by this time. What is your earned value?
1. $240,000
2. $270,000
3. $30,000
4. $30,000