Assignment:
Given an activity in an advertising project whose planed cost was $12,000 but actual cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client by pleased or angry?
Your answer must be typed, double-spaced, Times New Roman font (size 12), one-inch margins on all sides, APA format and also include references.