Calculate variance for all task


Question: Consider the tasks, durations, and predecessor relationships in the following network.

Activity Description

Immediate

Predecessor(s)

Optimistic

(Weeks)

Most Likely

(Weeks)

Pessimistic

(Weeks)

Te

Variance

A

---

4

7

10

 

 

B

A

2

8

20

 

 

C

A

8

12

16

 

 

D

B

1

2

3

 

 

E

D, C

6

8

22

 

 

F

C

2

3

4

 

 

G

F

2

2

2

 

 

H

F

6

8

10

 

 

I

E, G, H

4

8

12

 

 

J

I

1

2

3

 

 

 

 

 

 

 

 

 

 

 

1) Draw the network:

2) Calculate Te for all tasks (fill in the table):

3) Calculate variance for all tasks (fill in the table):

4) Determine all paths, their estimated durations, and their variances:

5) Identify the critical path:

6) What is the likelihood (probability) of completing the project in 42 weeks?