A firm wishes to determine the efficiency and utilization of a work center composed of 5 machines each working 16 hours per day for 5 days a week. A study undertaken by the materials management department found that over the past 50 weeks the work center was actually working for 16,000 hours, and work performed was 15,200 stan- dard hours. Calculate the utilization, efficiency, and demonstrated weekly capacity.