Solve the below problem:
Q: Ten (10) models of one hundred (100) parts each were taken from continuing process to establish a p chart for attributes. Calculate the upper control limit given that z is equal to three (3).
Model 1 2 3 4 5 6 7 8 9 10
Quantity 7 5 8 4 6 7 4 6 4 7