Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 45 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes.
Under the just-in-time philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and just-in-time manufacturing methods. If required, round percentages to one decimal place.
|
Traditional Philosophy |
Just-in-Time Philosophy |
Value-added time |
|
min |
|
min |
Non-value-added time |
|
min |
|
min |
Total lead time |
|
min |
|
min |
Value-added ratio (as a percent) |
|
% |
|
% |