Response to the following problem:
ABC, Flaydo inc. make flavored water and performing the following tasks in the beverage manufacturing process ,
Reviving and transferring ingredients storage 9.0 hours, Storing ingredients 270.0 hours ABC, Flaydo inc. make flavored water and performing the following tasks in the beverage manufacturing process ,
Reviving and transferring ingredients storage 9.0 hours, Storing ingredients 270.0 hours, transferring the ingredients from storage 4.5, bottling the water 3.0, transferring the bottles to a wait customer shipment 9.0 ,
(a) calculate the total cycle time of this manufacturing process
(b) calculate the manufacturing cycle efficiency of this process.