Problem 1: Imagine that the team planned to complete 30 story points in iteration, but only completed 25. Calculate the SPI.
Problem 2: The earned value to date is $2.2M and the actual costs to date is $2.8M, Calculate the CPI.
Problem 3: Now inform how the project is going?