The following information has been gathered for a project. Activity Activity Time (weeks) Immediate Predecessor(s)
A B C D E F G 4 7 9 3 14 10 11 --- A B B D C, D F, E
a. Draw the network diagram.
b. Calculate the slack for each activity and find the critical path. How long will the project take?