This information is gathered for a project to install a new machine lathe at Diamond Manufacturing Inc:
Activity Time Immediate Result
A 4 ---
B 7 A
C 9 B
D 3 B
E 14 D
F 10 C,D
G 11 F,E
Show the network diagram.
Calculate the slack for each activity and determine the critical path. How long will the project take?