Calculate the slack for each activity


Problem: Can you help me get started on this assignment? I'm really stuck!

The following information is known about a project...
Activity    Immediate Predecessor(s)    Activity Time (days)
A    -    7
B    A    2
C    A    4
D    B, C    4
E    D    4
F    E    3
G    E    5

Q1. Draw the network diagram for this project.

Q2. Determine the critical path and project duration.

Q3. Calculate the slack for each activity.

Q4. Estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 that probability that B-F-G will take more than 20 weeks or less.