Problem: Can you help me get started on this assignment? I'm really stuck!
The following information is known about a project...
Activity Immediate Predecessor(s) Activity Time (days)
A - 7
B A 2
C A 4
D B, C 4
E D 4
F E 3
G E 5
Q1. Draw the network diagram for this project.
Q2. Determine the critical path and project duration.
Q3. Calculate the slack for each activity.
Q4. Estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 that probability that B-F-G will take more than 20 weeks or less.