Problem: An office manager needs to know the size of Kanban that will be needed for her office. She knows that the average amount of work produced is 350 folders per day. The interoffice memo tray can contain 20 folders. It takes 1/2 day for the upstream to replenish the supply. Assume 100 folders safety stock. Calculate the size of the Kanban needed.