Calculate the scheduled completion time


The given data were obtained from a project to build a pressure vessel:

Activity    Duration    Predecessors
A    4 weeks    ---
B    4 weeks    ---
C    3 weeks    B
D    2 weeks    A, C
E    3 weeks    B
F    5 weeks    D, E, G
G    2 weeks    B
H    6 weeks    F
I    3 weeks    G
J    1 week      I

Construct a network for the project. Then review and answer (A) and (B).

(A.) Calculate the scheduled completion time and identify the critical path.

(B.) What is the slack time (float) for activities A, D, E, and G?